Your Condo's EV Load Study Says 18 Chargers. Here's What It Doesn't Tell You.
The short version
- A load evaluation measures spare power at the building's peak. Residents need energy overnight, which is a different and usually much larger number.
- The real limits are often the building's equipment (transformers, panels, feeders), and charging has to be balanced panel by panel.
- Measure first, use load management, and add chargers in stages before paying for a service upgrade.
If your board has looked at EV charging, you've probably seen a load evaluation. An engineer takes the building's electrical capacity, subtracts peak demand, and reports how many chargers will fit. That report is necessary. On its own, it's a poor guide to how many residents you can actually serve.
A real example
We reviewed a load evaluation for a 320-suite Toronto-area condo tower. The garage panel had about 208 kW of capacity. After a 20% safety margin and an estimated 91 kW peak, 75 kW was left. At 6.7 kW per Level 2 charger with 2:1 power sharing, that's about 22 chargers, trimmed to 18 after a buffer.
Eighteen chargers for 320 suites. The math is sound. What it leaves out is how EVs are actually used.
1. EVs need energy overnight, not power at peak
EV charging isn't a 24-hour load. Most Canadians drive well under 100 km a day, which is roughly 8 to 10 kWh in a modern EV. A 6.7 kW charger replaces that in about an hour and a half. The car may be plugged in all night, but it draws power for only part of that time, and not every car charges every night.
Now spread that same 75 kW over a 10-hour night. That's 750 kWh, enough for the daily driving of roughly 75 to 90 EVs, not 18. With load management, even if every car plugged in at once, each would get about 0.9 kW, or around 9 kWh by morning.
That's an illustration, not a design. But the gap between 18 and 75 is the point.
2. Peak demand is an estimate, and it isn't when residents charge
Many condo bills show only energy (kWh), not peak demand, so the peak is often estimated from equipment ratings. That's cautious, and it tends to overstate the real peak.
The peak also happens at a particular time: a hot summer afternoon for many buildings, or a cold late-winter stretch for a heated garage (this report found it in March). Residents mostly charge in the evening and overnight. Subtracting the year's worst moment, and then assuming EVs draw at that same moment, stacks two worst cases.
To its credit, the report recommended metering the garage panel with the first chargers and adding more as real data allows. That's the most important line in it.
3. The building's equipment is often the real limit
Spare capacity on paper still has to reach the parking spots. In this example the garage panel runs at 600 V, while Level 2 chargers run at 208 V or 240 V. That means a step-down transformer, a new panel and room to put them, before a single charger is connected. Older buildings may also have aging switchgear, full electrical rooms or long cable runs to the parking levels. None of that appears as a charger count, but it can be the biggest part of the cost.
4. Standard equipment sizes mean balancing panel by panel
Breakers, panels and transformers come in standard sizes. A 32 A charger needs a 40 A breaker, and every panel and transformer between the service and the charger has its own rating. A building can have spare capacity at the main service and still have a full garage panel. So chargers need to share power at the panel or transformer that feeds them, not only across the whole building.
The Canadian Electrical Code allows for this. Under Rule 8-106(10), chargers controlled by an EV energy management system are counted at the maximum load the system allows, not the total rating of every charger. Rule 8-500 then requires that the system never overload a circuit, feeder or service. A well-designed system lets a building connect far more chargers than its spare capacity suggests, while protecting each piece of equipment.
What boards should do
- Read the load evaluation for what it is: the safe power limit at peak, not the number of residents you can serve.
- Measure before you upgrade. Meter the panel that will feed the chargers and look at demand by time of day.
- Plan around overnight energy and load management.
- Check the infrastructure early: voltage, space for transformers and panels, and cable runs.
- Grow in stages as demand and data support it.
This isn't a case for ignoring the engineer. Load evaluations, permits and inspections exist for safety, and some buildings genuinely need a service upgrade. A load evaluation is where the conversation starts, not where it ends.
Talk to an honest EV charging advisor
If your board has a load evaluation and isn't sure what it means for residents, we'll review it with you and tell you plainly what it does and doesn't show, including when an upgrade really is the right call.
Talk to an honest EV charging advisor
Sources
- Canadian Electrical Code, Rules 8-106(10) and 8-500, explained in IAEI Magazine: Electric Vehicle Energy Management System (EVEMS): clarifying the mystery
- Technical Safety BC, Information Bulletin IB-EL 2023-05: EVSE and EVEMS
- CAA, How far can I drive before having to recharge my electric vehicle?
- EV charging load evaluation for a Toronto-area condominium (engineering report, 2023; building not named)